Our team recently completed a project in Chichester, where it drilled ten 160-m boreholes for our client ISO Energy

The scope of work was to drill 11 m apart; however, the client advised that there may be restrictions due to overhanging trees and a local drain run. We mobilised our 909 geothermal drilling rig, along with one mud recycling system. Wastewater removal was also arranged. The project duration was 12 days, including mobilisation and demobilisation.